| Site | Status | Notes |
| Lower Saltonstall Tot Lot 149 Main Street | Design Process Starting FY 2028 | |
| Victory Field Playground 40 Orchard Street | Design Process Starting FY 2028 | |
| Walker Pond Park Project (CPA funded) | Concept Design + Community Engagement (Summer 2025 to Winter 2026) | |
| Historic Cemeteries: Old Burial Ground and Common Street Cemetery (CPA Funded) | Design Development & Construction Drawings (Summer - Winter 2026) | |
| Sulivan Playground Arlington and Mount Auburn Street | Construction Drawings - 90% (Fall 2025) | Construction Starting in FY27 |
| How Park Project Pleasant and Bacon Street | Construction (Spring - Summer 2026) | |
| Bemis Park Project Waltham Street | Construction (December 2025 to Summer 2026) | Park sections will open when completed |
| Victory Field: Phase II 40 Orchard Street | Construction (Mid-Aug 2025 to Fall 2026) | Park will open in fall 2026, and the field will open in spring 2027 |
| Saltonstall Park 149 Main Street | Opened Spring 2026 | Pavillon Canopy - In Progress |
| Lowell Playground Lowell and George Street | Park Opened October 2026 | |
| Arsenal Park: Phases A + B 485 Arsenal Street | Park Opened June 2025 | |
| Moxley Park Court Renovation Project Westminster Ave | Project Completed | |
| Filippello Spray Park Project 191 Grove Street | Project Completed 2024 |
Open Space Project Construction Timeline Capital Improvement Projects (2026-2032)
The City of Watertown’s FY27 Budget includes several park capital improvement projects (CIP). The table below outlines the park project construction timeline. These timelines may be subject to change.
Project | Construction Timeline | CIP FY | Notes |
Sullivan Park | Summer 2026 | FY27 | |
Walker Pond | 2027 | FY27 | Applied for CPA Funds |
Lower Saltonstall Tot Lot | 2028 | FY27 | |
Victory Field Playground | 2029 | FY28/29 | |
Victory Phase 3 | 2028 | FY27/28 | |
How Park Phase 2 | 2030 | FY29/30 | |
Filippello Pickleball | 2030 | FY30 | Moved up from FY31 due to community interest |
Moxley Park Field | 2030 | FY30/31 | Years subject to change pending decisions regarding the Middle School |
Filippello Grove Playground | 2031 | FY30/31 | |
Filippello Arlington Playground | 2032 | FY30/32 | Design process will be combined with the Grove Playground. Construction will take place after Grove |